Sewage break 300 building & Bus Path

Home Forums Town Homes – ongoing projects Sewage break 300 building & Bus Path

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #490
    secretary
    Moderator

    Description:

    March 2nd 2022 there was a sewer break in the 300 building. Water and sewage backed up and one resident had damage inside the unit. Residents were not able to use their facilities for a few days. A port potty was provided for the duration it took to complete the repairs. A plumber unblocked and located the break. Stutzman Gerbaz repaired the broken sewer line March 9th.

    [pdf-embedder url="http://twinridgehoa.org/wp-content/uploads/2022/04/Daily-Report-4-22.03.08-Twin-Ridge-Sewer-Service-Repair.pdf" title="Daily Report #4 - 22.03.08 Twin Ridge Sewer Service Repair"]

    #515
    cliffweiss202
    Participant

    I just got off the phone with Mountain West Insurance. The HOA does have coverage from CAU Insurance to reimburse for some proportion of the mitigation. I have not seen an invoice from Gerbaz but we did pay All Valley Resource Plumbing and Colorado Site Services (porta-potty) for their portion of the work.

    If you have questions, Mark was the primary HOA point-man on the work done. Also be aware that Scotty submitted a claim to CAU for damage caused by the sewer backup.

    #544
    bgragnolati
    Participant

    What are we thinking for the bus path? I am willing to spend a couple hours out there this week, but maybe we wait until after this snow. I do not think we need to spend a lot on this if some of us want to help out with simple tools. But I’d like to know others thoughts…

    #550
    Danno
    Keymaster

    Ben, Marc and Polo and I agreed to wait till May 1st and let it dry out a little longer. Mark will start in all earnest May 1. We will have the same contractor (Stutzman Gerbaz) who did the earthmoving and the sewer repair, restore the bus path to its original state, grade and alignment. If the contractor can improve aesthetically or hydrology wise for the same price as original restoration it would be welcome. We will have to get a quick estimate, scope of work agreement and as a board approve. Aim to get it done in the first two weeks of May…
    Did I miss anything?

     

    Some Rocks along the sides?Grade the steep section.

    #556
    Danno
    Keymaster

    Scotty’s water damage

    Sewer/ water damage Scotty’s